Semi-Annual Report 2013-2014

Renovation projects France

Property: Neuilly-sur-Seine, Paris, 52 Boulevard du Parc

Name of project: Newtime

Scope of renovation:

Full renovation and transformation into energy efficient building (labels, BREAM “excellent”, HQE BBC)

Increase space by 20%

Use of water of the Seine river to heat and cool the building

Double layer facade

Start of works: March 2012

End of works: March 2014

Construction costs: EUR 58 million

Marketing/tenant fitting out: EUR 5 million

Tenant: Active marketing with 3 big letting agents

Status of renovation:

Works started as planned in March 2012

Demolition and asbestos removing are completed

New facade constructed

75% of workload are done

Property: Neuilly-sur-Seine, Paris, 20-26 Boulevard du Parc

Name of project: Imagine

Scope of renovation:

Full renovation of 75% of usable space

Asbestos removal

Replacement of all existing technical equipment

Installation of a new inner facade

New security and fire equipment

Labels HQE BBC

Start of works: April 2012

End of works: June 2013

Construction costs: EUR 18 million

Marketing/relocation costs/tenant fitting out: EUR 2 million

Tenants: TMC Regie, Cisac, Grassroots (existing), first new tenant (Promethean)

Status of renovation:

100% of workload are done

Property: Gennevilliers, Paris, 1 Promenade de la Bonnette

Name of project: Chaganne

Scope of renovation:

Full renovation of inner space

Full renovation of courtyard and facades

Extension of entrance hall

50 % of the work force relocated in temporary offices

Start of works: December 2012

End of works: March 2014

Construction costs: EUR 9 million

Temporary relocation costs: EUR 4.5 million

Tenant: Europ Assistance

Status of renovation:

80% of workload are done